Glenwood Springs – Mitchell Creek Electric Transmission Line Rebuild

Current and Planned Work

Friday, April 26, 2024

During the week of April 29, 2024, crews will continue digging foundations for poles north of Highway 6 between Traver Trail and Highlands Drive.

On April 29 and 30, construction crews will use helicopters to assist in delivering materials and installing transmission poles in areas with steep terrain and limited access. Helicopter activity is expected from 7 a.m. until 7 p.m. Individuals required to temporarily evacuate have been notified.

If you are required to temporarily evacuate, please ensure all residents and pets are not home during this period. Please also consider moving your outdoor furniture and movable items to a secure location, to avoid being damaged by the helicopter’s down-draft.

Schedules are subject to change.